What does it mean when earned value is above planned value?
A) The project is ahead of schedule.
B) The project is behind schedule.
C) The project is exactly on schedule.
D) Earned value has no relation to planned value.
Correct Answer:
A) The project is ahead of schedule.
What does it mean when earned value is above planned value?